Technical news
Stay ahead of the competition with the latest technical news and updates.
Find out moreApril 2024
We are pleased to confirm that NHBC Building Control Services Ltd was registered as a Registered Building Control Approver effective from 6 April 2024. The registration extends across England and Wales and covers all building types including high risk buildings that have met the transitional provisions and will remain with NHBC Building Control through to completion.
All NHBC Building Control colleagues have successfully registered with the Building Safety Regulator in accordance with the transitional arrangements.
Under Regulation 38 of The Building Regulations 2010 you are required to provide fire safety information to the Responsible Person for buildings that are classified as ‘relevant buildings’ under the Regulatory Reform (Fire Safety) Order 2005 (ie, flatted developments with common areas or non-residential buildings/parts of buildings).
The changes to Building Regulations implemented on 1 October 2023 contained a requirement on new Initial Notices submitted after that date, for the Responsible Person to confirm that they had received the fire safety information and that it was sufficient for them to understand, operate and maintain the building in respect of those works.
The Building (Approved Inspectors etc and Review of Decisions) (England) Regulations 2023 which came into force on 1 October 2023, contained transitional provisions indicating that these additional requirements would only apply to new schemes. However, the Building (Registered Building Control Approvers etc) (England) Regulations 2024 which came into force on 6 April 2024 and supersede the 2023 regulations, failed to carry across these transitional provisions.
The impact of this is that from 6 April 2024 this additional confirmation from the Responsible Person will now be required on all applicable projects, regardless of when the Initial Notice was submitted.
Practically, this means that where sites have a previous Regulation 38 condition applied, which would have only asked for confirmation of the Responsible Person, we will need to update that condition to reflect the new requirements. In cases where you may have previously provided information in respect of the Responsible Person and the condition has been cleared, it will be necessary for us to reapply the updated condition to unfinalled plots and for you to provide the additional information.
In summary:
Please note this only applies in England and only applies to plots in a relevant building as defined above To assist you in providing this information we have provided a Regulation 38 proforma.
The provision for the automatic lapse of Initial Notices was introduced as part of the changes to the Building Regulations introduced on 1 October 2023. These changes were subject to transitional provisions that ended on 6 April 2024.
Initial Notices accepted on or after 1 October 2023
The following provisions apply to all sites where the Initial Notice was submitted on or after 1 October 2023.
For work on an Initial notice not to lapse, work should have commenced within three years of your Initial Notice being accepted or deemed accepted. This means that if work does not commence within this timeframe, the Initial Notice becomes invalid. This requirement is plot specific.
For example, if you submit an Initial Notice for 100 plots and three years after the anniversary of the Notice being accepted or deemed accepted, only 75 of those plots have commenced, the remaining 25 plots would be removed from the Initial Notice. If you wished to continue to build out the 25 plots that had not commenced, you would need to submit a new Initial Notice for these plots in line with the latest regulations.
The Building Regulations define commenced as:
Complex building: Construction work on a complex building is considered commenced when the foundations and the lowest floor structure are completed. A complex building includes:
Building or horizontal extension: For standard building construction or horizontal extensions, work is considered to be commenced when the sub surface structure, including foundations, basements levels (if any), and ground floor structure is completed.
Other building work: For any other types of building work not falling under the above categories, work is considered commenced upon completion of 15% of the work specified in the Initial Notice.
Initial Notices accepted or deemed accepted before 1 October 2023
For Initial Notices that were accepted or deemed accepted before 1 October 2023, the new provisions relating to lapse of Initial Notice will not apply, provided that building work has commenced on site by 6 April 2024. This means that sites that have not had a recorded site inspection before 6 April 2024, will fall under the requirements of lapse of Initial Notice.
For example, any Initial Notice with an acceptance or deemed acceptance prior to 6 April 2021, with no site start, will automatically lapse on the 6 April 2024.
Sites that do not meet the transitional provisions will be subject to the new provisions relating to the automatic lapse of plans in the same way as new Initial Notices accepted after 1 October 2023. This means that the following requirements will apply:
There are crucial steps required to comply with the commencement requirements for building work, as outlined in the regulations. It is essential to ensure that you follow these procedures to avoid any delays or complications on your project.
a) Notice before starting work: At least two working days before the start of building work, it is mandatory to provide a notice to us. This notice should clearly state your intention to commence work and specify the start date.
b) Notice of commencement: Not more than five working days after the commencement of work, you must provide a notice to us confirming that work has commenced. This notice is crucial to ensure compliance with the regulations.
Response to Rejection Notices: if we reject your notice of commencement, we will inform you of the reasons and the process to follow if you disagree with the rejection.
We have provided proformas for start and commencement notices for your use which are available here.
Here are some important tips to help you stay compliant with the new Building Regulations in relation to lapse of Initial Notice:
We understand that navigating these regulations may seem complex, but we are here to assist you. If you have any questions or concerns about your project or the status of specific plots, please contact your NHBC surveyor.
Stay ahead of the competition with the latest technical news and updates.
Find out moreTo help you interpret and apply the NHBC Standards we produce Technical Guidance Documents on the page below.
Find out moreNHBC is uniquely placed to offer relevant, best practice technical training.
View coursesYour essential guide to house building from foundations to roofs and finishing.
Read moreTechnical queries and quotes
Any technical information contained on this website is produced by NHBC as guidance solely for all our builder customers as to how to interpret the technical requirements in relation to the warranty cover provided by NHBC under its Buildmark, Buildmark Choice, Buildmark Link, Buildmark Solo, Buildmark Connect or any similar product from time to time. It has not been created or intended for distribution or use outside of that purpose. The technical information contained on this web page does not constitute advice and is not to be relied upon by any third party. Nothing on this web page is intended to, nor should it be taken to, create any legal or contractual relationship. Any third party who chooses to rely upon the information contained on this web page shall do so entirely at their own risk and NHBC accepts no duty of care or liability, however caused, in connection with its use or reliance by any third party.